Project Summary

CLIENT:

Skanksa via Hampshire council

PROJECT TIMEFRAME:

10 days installation

SCOPE OF WORK:

Remove old cattle grid and base and replace with new pre cast concrete bases and new design steel works. Replace side fencing with new like for like.

As part of our cattle gird contract with Skanska and Hampshire council we installed this new laarge cattle grid at the Cadnam roundabout.

This was a challenging grid due to the long diversion route putting pressure on the workforce to complete the job quickly.

Whilst we undertook this work the snow came down up to about 15cm. With no choice but to carry on, Triangle covered the grid with tarpaulins and fencing to use large space heaters. These were needed to keep the concrete temperature up so the 100 newton grout could set properly in the time frame.

Thanks to our dedicated team of installers and project manager Mark, the grid was opened on time despite the weather.